December 2025
• Turner Construction provided a tour of the Library's construction site to the Board of Trustees and Library Administration.
• The Library Board of Trustees approved furniture bids from Inspire Workplace Interiors and from American Interiors.
• The Library Board of Trustees approved a resolution authorizing the Director and Fiscal Officer to extend the RFC Contracting contract for Owner's Representation services.
November 2025
• The Euclid Public Library Board of Trustees approved the purchase of two wall-mounted gaming units for the Teen area and one interactive gaming table for the Children's area.
• Approved a Communico contract to provide software for managing library events, reserving meeting spaces, and broadcasting messages.
• Approved Arreya Lighting Addendum for the Library's Donor Recognition Wall.
October 2025
• Library Board of Trustees approved a quote to purchase computer equipment and related infrastructure from vTechio for the renovated Library.
• Turner Construction continued work on the exterior of the building with masonry tuck pointing, exterior painting and new bollard installation.
September 2025
• Director Kacie Armstrong, Owner’s Representative Roger Riachi, and Turner Construction provided renovation tours to students in the Euclid School District’s Construction Management program.
• The Library Board of Trustees approved a contract with Blitz Studios to produce a renovation video for the Marketing Department.
• The Board approved a contract with Arreya to design and construct a donor wall at the entrance of the Main Library at 631 East 222nd Street.
• The Board approved a resolution to work with the Euclid School District to create an illustrated book related to the renovation project.
• The furniture selection process with Bialosky Cleveland for the renovated building was completed.
August 2025
• Turner Construction erected metal studs to frame priority walls in the Main building at 631 East 222nd Street.
• The Euclid Public Library Board of Trustees held a special meeting to discuss reductions in state funding for Ohio libraries.
• Euclid Public Library celebrated its 90th anniversary on August 9 with a festival at Sims Park.
July 2025
• Turner Construction reported that the renovation project is on schedule to open in Spring 2026.
• The Library Board of Trustees authorized the Fiscal Officer to solicit statements of qualifications for landscape architect services for the Main Library at 631 East 222nd Street.
June 2025
• Turner Construction began trenching the concrete floor for plumbing and electrical underground work.
• Euclid Public Library began the selection process for furniture for the Main building at 631 East 222nd Street.
May 2025
• Turner Construction continued the demolition of the Main Library on East 222nd Street.
• The Library Board of Trustees approved the purchase of an Automatic Material Handler for the renovated Library at 631 East 222nd Street.
• Euclid Public Library participated in the Neighborhood Stroll and hosted an Open House on May 30 at the temporary location at 475 E. 185th Street.
April 2025
• Turner Construction began demolition and renovation of the Main Library on East 222nd Street.
• EPL at 185th opened to the public on Monday, April 14.
• The Library Board approved the Turner renovation contract (GMP #2) for the 631 East 222nd library location.
March 2025
• On March 14, Euclid Public Library hosted a Renovation Launch to celebrate the start of construction.
• The Main Library at East 222nd Street officially closed to the public on March 14.
• The Library Board approved the Turner renovation contract (GMP #1) for the 475 E. 185th temporary location.
• Armbruster Moving & Storage began transferring materials and furniture from the Main Library to EPL at 185th.
February 2025
• Turner Construction began renovating the Library's temporary location at 475 E. 185th Street.
• Town hall meetings were held to share renovation updates and temporary service plans with the community.
• The Library Board of Trustees approved a proposal to move and reconfigure shelving from Library Design Associates.
• Packing began in staff spaces, closets, and storage areas.
• The City of Euclid approved a permit for a new electronic sign at the renovated library, scheduled for installation in 2026.
January 2025
• Euclid Public Library's Administrative team moved to the Lakeview office space on January 30.
• The Library met with Bialosky and Turner Construction to determine moving and closing dates for the renovation project.
• Sunlight General removed the solar panels from the library roof in preparation for upcoming construction.
Stakeholders and patrons are encouraged to stay up to date on the renovation project by visiting the Library Renovation section of the website, signing up for our eNewsletter, and following us on social media.